Our process

How a tile project runs with Prominent Tile

Here is what to expect from your first message through the final walkthrough.

1. Tell us about the space

Send photos, rough measurements and your goals through Start Your Project, or call or text 832-497-8136.

2. Review scope and site conditions

We talk through the scope, tile choices, layout and timing, and visit the space when the project is a good fit.

If you don’t already have tile selected, you’re welcome to meet with a local designer at no cost to you, at a tile distributor we work with. Once the tile has been selected with the designer, Mauricio takes the lead on ordering and purchasing it.

3. Receive a written proposal

You receive an estimate describing the scope of work.

How changes are handled

Any changes outside the discussed and signed contract are handled with a written change order for the task desired.

4. Install and complete the walkthrough

On residential projects, we protect existing floors and finished areas with floor protection rolls, zip doors and plastic sealing of openings. We remove existing materials where needed and prepare the substrate. Wet areas get a waterproofing system installed to the manufacturer’s instructions. Installation follows TCNA guidelines and manufacturer recommendations. We clean the work area and walk through the finished installation with you.

Top-down view of a marble-look porcelain shower with basketweave mosaic floor and niche

Prominent Tile only performs tile assembly installations — substrate, waterproofing and tile. We do not perform plumbing, glass, electrical, framing or other trades work. Clients and builders bring their own trades for those parts of the project.

On a real job

What the installation looks like, step by step

These photos are from one of our recent projects, a second-floor curbless shower in Houston. Every job is different, but the order of work is the same: fix what is underneath, waterproof and test, then set the tile.

Wall after demolition showing circles of thinset where the old panels were spot-bonded instead of fully covered
1. Demolition and inspection. Removing the old panels showed spot dabs of thinset instead of full coverage.
Deteriorated subfloor around the old shower drain after demolition
2. Finding the damage. Water had reached the subfloor around the drain.
New framing members installed in the opened floor below the shower
3. Structure. Framing repaired to a structural engineer’s report.
New AdvanTech subfloor panels being measured with a tape measure
4. Subfloor. New AdvanTech subfloor, measured and fastened.
wedi board shower walls fastened in a grid with washers before waterproofing
5. Walls. wedi board, with sealant on every seam and screw.
Numbered pieces of a custom pre-sloped foam shower tray laid out around the drain
6. Slope. A custom pre-sloped tray, ¼″ per foot to the drain.
wedi Subliner Dry sheet membrane with sealed seams over the shower floor
7. Waterproofing. wedi Subliner Dry over the tray, seams sealed.
Standing water over the FLO FX drain flange during the 24-hour flood test
8. Flood test. Water held for 24 hours before any tile.
Wet-cutting a large black porcelain panel with a circular saw guided along a straight edge
9. Cutting. Large panels are cut wet along a straight edge.
Large black veined Daltile Panoramic porcelain panels set on the shower walls during installation
10. Setting. Panels set with full mortar coverage.
Square tiled-in drain in the sloped large-format porcelain shower floor with water running
11. Finished. A tiled-in drain in the curbless floor.

Read the full case study for this shower